Every new house type got faster; multiple dwellings did not
New buildings, median days to issue. Bar is LTM Sep-2026; ticks mark the two earlier periods.
Median days to issue went from — to — in LTM Sep-2026, but the slowest 10% did not improve: P90 went from — to — days.
New buildings, median days to issue. Bar is LTM Sep-2026; ticks mark the two earlier periods.
Share of permits (grey) and of project value (colour), LTM Sep-2026.
Extra median days when a month has 10 more applications of that type. Line is the 95% range; filled dots are statistically clear.
Supporting evidence · 2017–2025 cohortsDays vs the average month, comparing each month only with months of the same year.
Supporting evidence · 2017–2024 cohortsWhat replaces a demolished building, by period of the demolition.
An upper bound: the division also handles other work. Department staff and median days by year are on the Resources page.
P90 is the number of days within which 90% of permits are issued; only the slowest 10% take longer. The gap to the median is wide because most permits are quick alterations, while the slowest 10% are mostly new buildings and demolitions, and the clock also counts time waiting on applicants.
Median and P90 days by month issued (lines, left axis); permits issued (grey bars, right axis). Markers: 1 multiplex permit stream (early 2025), 2 salvage and abatement folded into demolition (late 2025), 3 online portal for low-density housing (Nov 2025).
Share of permits issued within N days of application.
Median days; P90 for LTM Sep-2026 in the last column.
Permits issued in each period, by how many periods earlier they were submitted.
New buildings carry over more: — of those issued in LTM Sep-2026 were submitted the year before, against — a year earlier.
Mixed use means more than one recorded use; "with housing" when one of them is dwelling. Last column is P90 for LTM Sep-2026.
LTM Sep-2026. Grey is share of permits; colour is share of value.
Multiple dwelling permits tripled after the 2023 multiplex zoning, so their mix changed; compare with care. Last column is median project value.
Largest categories in LTM Sep-2026. Last column is P90.
Every permit number counts as an application, including numbers never issued. Grey is not issued yet: still pending, withdrawn or refused. Recent months are still in the queue.
Extra median days per 10 more applications of that type in a month, with month and year controls. Line is the 95% range; filled dots are statistically clear.
Supporting evidence · 2017–2025 cohortsDays vs the average month in the same year, by month opened.
Supporting evidence · 2017–2025 cohortsA site is a demolition and a new building at the same address, issued within two years of each other.
New building on each site, by specific use. Some LTM Sep-2026 sites still wait for their new building, so pairing is lower this year.
Redevelopment sites by local area, top 10 in LTM Sep-2026. A March 2026 City memo notes demolition permits are being decoupled from building permits, which fits the fall in same-day issue.
Budget and staffing are published by calendar year, so this page uses calendar years, not the LTM periods.
Development, Buildings and Licensing FTE (bars; 2024–25 are budget forecasts, hatched) and median days to issue by year issued (line). A match in timing, not proof of cause.
2025 budget divided by permits issued in 2025.